Construction Closures 3/17-3/21

Jump to:

CONSTRUCTION CLOSURES

Walnut Street Bridge

The Walnut Street Bridge carrying pedestrian and bicycle traffic across the
Tennessee River is now closed for renovation. The estimated reopening date
is September 2026. Detours via the Market Street Bridge and Veterans Bridge
are now posted. Visit www.walnutstreetbridge.com for more information.

3400 Rossville Blvd at E 34th Street

The following locations will have restrictions in place from Tuesday, March
18th until Monday, March 31st between 9 AM and 3 PM (weekdays only) for
sewer replacement:

The northbound right lane of Rossville Blvd will be closed

E 34th Street at Rossville Blvd. will be closed

Market Street from Aquarium Way to Frazier Ave

The Market Street Bridge between Frazier Ave and Aquarium Way will fully
close to vehicle traffic on Tuesday, March 18th from 7 PM until 11 PM per
the request of the Chattanooga Division of  Arts, Culture, and Creative
Economy. The sidewalk located on the east side of the bridge will close
from 4 PM until 11 PM.  Brief, intermittent closures (of a couple of
minutes) will take place on the west sidewalk but will be kept open for the
majority of the evening. Detours via 4th Street, HWY 27, Manufacturers
Road, and Cherokee Blvd will be posted.

14th Street Neighborhood Bikeway Project - Phase 1

Phase 1 of the 14th Street Neighborhood Bikeway Project will begin
Wednesday, March 19th through Friday, March 21st between Central Ave and S
Holtzclaw Ave. Intermittent brief closures may occur, however, two-way
travel will be maintained by the use of flaggers. Please use caution as
CDOT crew members work within the right of way.

2025 PAVING AND RESURFACING SCHEDULE FOR 3/17-3/21

The City of Chattanooga Department of Public Works in conjunction with our
contract crews has scheduled the following locations for resurfacing for
the week of Monday, March 17th through Friday, March 21st (weather
permitting):

N Moore Road between Brainerd Road and Shallowford Road

The work is estimated to take the full week due to the number of lane
miles to be paved. Crews will close multiple lanes at a time, but will
maintain single lanes in each direction for the duration. Driveways and
intersections may briefly close while crews mill and resurface past these
points. All work is weather permitting and subject to change without
notice.

View CDOT's map of events and road closures
<https://nam04.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.google.com%2Fmaps%2Fd%2Fedit%3Fmid%3D1CNXFi5H3Ix1IELX9S02_63K5WVg%26ll%3D35.04566329192144%252C-85.30153052466392%26z%3D14&data=04%7C01%7Cjdmaples%40sbgi.mail.onmicrosoft.com%7C1a6d5db7d6474168ec2208d9e2a4c5b4%7C897dbc0dc02d43479a713e589c67f8aa%7C0%7C0%7C637790019584424943%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=jb9JmWQW3Nm9zY5gUz3CvxJExIzKla46aQkFMLF%2FyKc%3D&reserved=0>
for full details of these activities and other projects underway in our
public space.